| 4580067 |
false |
|
true |
1. The industry has submitted project cost as Rs. 1.10 Crores in application of TSIPASS and OCMMS but whereas in EC order it was mentioned as Rs. 6.20 Crores. Please justify.
2. The industry shall submit compliance on EC conditions.
3. The industry shall submit existing and expansion of water consumption & wastewater generation and its treatment system and Solid waste & its disposal.
4. The industry shall pay balance consent fee of Rs. 1,90,200/- on investment cost of Rs.6.20 Crores under Red category.
|
2023-05-12 15:21:30.656 |