The industry shall submit the following details for further processing of application:-
As per the TOPO plan submitted by the industry the proposed site is adjacent to the Road. As per the siting Guidelines from Transportation / Communication System the industry shall follow the as below:
The following width of buffer zone shall be maintained from the Road Land Boundary*:
1. National Highways – 50 Mts., 2. State Highways – 40 Mts., 3. MDR / Village Road – 20 Mts.
*Road Land Boundary means the boundary of the road upto which land is acquired for road purposes.
As per the TOPO plan, a temple and houses are located nearby the proposed site. Hence, the applicant shall submit the revised TOPO plan by mentioning the exact distances from the proposed site.
|