6010178 true Approved. false 2025-06-17 17:51:24.006
6010185 false false 2025-06-17 17:57:16.721
6010225 false false 2025-06-17 18:03:30.01
6010237 true CFO order approved false 2025-06-17 18:05:34.32
6009367 false false Actual fee to be paid is Rs. 4,50,000/-. Paid Rs. 100/- only. Hence, balance fee to be paid is Rs. 4,49,900/-. 2025-06-17 16:10:10.031
6010730 false false 2025-06-17 23:42:55.492
6011004 false false Dear Sir, 1.We have completed 52% of our concreting works at Sitammasagar Multi-purpose (SSMP) project. Hence, we have planned to reduce the capacity from 2352 TPD to 1176 TPD for the balance concrete works. We have already submitted a letter to your good office in this regard on 28.05.2025 and herewith attached the same for your ready reference please. 2.We have released some of the machinery pertaining to the RMC plant from the SSMP project to our other projects. Hence, the cost has reduced from Rs. 2.66 crores to Rs. 1.22 crores. The same has been certified by a Chartered Accountant and submitted to your good office in line with the requirement. The CA certificate is also attached for your ready reference please. Regards. 2025-06-18 11:32:20.344
6011163 false false 2025-06-18 12:20:33.813
6011180 false false 2025-06-18 12:25:04.149
6011250 false false 2025-06-18 12:41:56.293