| Id: | 1685236 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2018-11-12 16:45:34.394 |
| File Note: | the Committee recommended to reject the CFO & HWA (expansion) applications of the industry for the following reasons: 1) The industry has not provided additional ZLD system as per CFE issued for expansion. The existing MEE is not sufficient to treat the proposed HTDS effluents generation i.e., 40.85 KLD for part of expansion capacity i.e., 813 Kg/day. 2) Not provided online pH meters to the scrubbers. prepare rejection order |
| Inspection: | false |
| Inspection Note: | |
| Officer: | TSPCB053 |
| Reject: | false |
| Reject Note: | |
| Role: | HO JCEE HYD |