Show ApplicationProcessingDetails

Id: 1781456
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2019-01-11 17:52:39.804
File Note: 2. The industry has obtained CFE of the Board for production of Boiled Rice – 40 TPD vide order dated 05.02.2018. As per the CFE order, the industry shall construct and commission Effluent treatment Plant(ETP) along with the commissioning of the industry. However, as per the Regional Officers report, the industry has not constructed ETP.
Inspection: false
Inspection Note:
Officer: TSPCB032
Reject: false
Reject Note:
Role: ZO HYD AEE1