| Id: | 4151187 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | As per the documents submitted, the proponent has applied for CFE (expansion) for additional product. Hence kindly submit the investment details for the proposed additional product along with water consumption and wastewater details. |
| Date Created: | 2022-10-25 10:33:47.837 |
| File Note: | As per the documents submitted, the proponent has applied for CFE (expansion) for additional product. Hence kindly submit the investment details for the proposed additional product along with water consumption and wastewater details. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | TSPCB058 |
| Reject: | false |
| Reject Note: | |
| Role: | RO EE |