| Id: | 4473008 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | Self certificate and process flow chart. Approx 1 crore project.For air prevention highted chimney is proposed, along with dust and fume arrestor.Water consumption is very less in quantity. Kindly issue approval as sooner as possible. Thanks in Anticipation of favourable action. |
| Date Created: | 2023-03-17 21:58:12.482 |
| File Note: | Self certificate and process flow chart. Approx 1 crore project.For air prevention highted chimney is proposed, along with dust and fume arrestor.Water consumption is very less in quantity. Kindly issue approval as sooner as possible. Thanks in Anticipation of favourable action. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | SAGANagar655330 |
| Reject: | false |
| Reject Note: | |
| Role: | Industry |