Show ApplicationProcessingDetails

Id: 4561887
Approve: false
Approve Note:
Clarification: true
Clarification Note: 1. The industry has submitted project cost as Rs. 100.40 Crores but whereas in CFE expansion order issued by the Board it was mentioned as Rs. 120.50 Crores. Please justify. 2. The industry shall pay balance consent fee of Rs. 93,750/- on investment cost of Rs.120.50 Crores for 4 years.
Date Created: 2023-05-03 14:02:10.945
File Note: 1. The industry has submitted project cost as Rs. 100.40 Crores but whereas in CFE expansion order issued by the Board it was mentioned as Rs. 120.50 Crores. Please justify. 2. The industry shall pay balance consent fee of Rs. 93,750/- on investment cost of Rs.120.50 Crores for 4 years.
Inspection: false
Inspection Note:
Officer: TSPCB031
Reject: false
Reject Note:
Role: RO EE