Show ApplicationProcessingDetails

Id: 4754652
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2023-08-16 18:19:38.314
File Note: Sir, even after raising the query, you have not entered the correct line of activity in the self certification, the material balance between raw material and product along with solid/hazardous waste generation is not correct, disposal of slag and waste acid(if there is any) is not mentioned and the total project cost is less than the quotation submitted for the machinery. You are requested to clarify the above things before applying again for the consent. Hence rejected.
Inspection: false
Inspection Note:
Officer: TSPCB072
Reject: false
Reject Note: Sir, even after raising the query, you have not entered the correct line of activity in the self certification, the material balance between raw material and product along with solid/hazardous waste generation is not correct, disposal of slag and waste acid(if there is any) is not mentioned and the total project cost is less than the quotation submitted for the machinery. You are requested to clarify the above things before applying again for the consent. Hence rejected.
Role: RO EE