| Id: | 4944117 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | As verified from the EMP report submitted by you along with CFE application, it is observed that the unit is already established and under operation. In this regard Pl furnish the copy of SSI registration issued by GM DIC Ranagreddy, Licence issued by Inspector of Factories & Certificate issued by Inspector of Boiler for taking decision on the application. |
| Date Created: | 2023-12-05 14:47:30.842 |
| File Note: | As verified from the EMP report submitted by you along with CFE application, it is observed that the unit is already established and under operation. In this regard Pl furnish the copy of SSI registration issued by GM DIC Ranagreddy, Licence issued by Inspector of Factories & Certificate issued by Inspector of Boiler for taking decision on the application. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | TSPCB022 |
| Reject: | false |
| Reject Note: | |
| Role: | ro ee |