1. The proponent has submitted site plan in chart mentioning orange colour i.e., for Block C1 as 6,722 sq.mtrs. But, whereas in EMP report the proponent as mentioned it as 6,277 sq.m. Please justify.
2. The proponent has submitted Block C1 lease deed document for a period of 2 years only. Hence, the proponent shall submit registered lease deed document for a period of 7 years.
3. The project has not submitted Block wise compliance report on the of CFO conditions issued by the Board.
4. The proponent has not submitted water balance and chart of STP along with facilities.
5. The proponent has not submitted effluent characteristics.
6. The proponent has not submitted details of hazardous wastes like cotton waste, Paint residue, sealant residue, paint & sealants containers, BMW details, Drilling scrap & packing waste.
7. The proponent has not submitted details of Floor moping, Air cooling, Sanitation, Domestic effluents, Fire Storage Tank & paint both wastewater.
|
| Reject Note: |
1. The proponent has submitted site plan in chart mentioning orange colour i.e., for Block C1 as 6,722 sq.mtrs. But, whereas in EMP report the proponent as mentioned it as 6,277 sq.m. Please justify.
2. The proponent has submitted Block C1 lease deed document for a period of 2 years only. Hence, the proponent shall submit registered lease deed document for a period of 7 years.
3. The project has not submitted Block wise compliance report on the of CFO conditions issued by the Board.
4. The proponent has not submitted water balance and chart of STP along with facilities.
5. The proponent has not submitted effluent characteristics.
6. The proponent has not submitted details of hazardous wastes like cotton waste, Paint residue, sealant residue, paint & sealants containers, BMW details, Drilling scrap & packing waste.
7. The proponent has not submitted details of Floor moping, Air cooling, Sanitation, Domestic effluents, Fire Storage Tank & paint both wastewater.
|