| File Note: |
1. The project has again not submitted Block wise compliance report on the of CFO conditions issued by the Board.
2. The proponent has again not submitted water balance and chart of STP along with facilities.
3. The proponent has again not submitted effluent characteristics.
4. The proponent has again not submitted details of hazardous wastes like cotton waste, Paint residue, sealant residue, paint & sealants containers, BMW details, Drilling scrap & packing waste.
5. The proponent has again not submitted details of Floor moping, Air-cooling, Sanitation, Domestic effluents, Fire Storage Tank & paint both wastewater.
|
| Reject Note: |
1. The project has again not submitted Block wise compliance report on the of CFO conditions issued by the Board.
2. The proponent has again not submitted water balance and chart of STP along with facilities.
3. The proponent has again not submitted effluent characteristics.
4. The proponent has again not submitted details of hazardous wastes like cotton waste, Paint residue, sealant residue, paint & sealants containers, BMW details, Drilling scrap & packing waste.
5. The proponent has again not submitted details of Floor moping, Air-cooling, Sanitation, Domestic effluents, Fire Storage Tank & paint both wastewater.
|