| Id: | 5330738 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | As per process flow chart submitted, Boiler is proposed to be installed. But, the proponent has not submitted details of capacity of Boiler and its Air Pollution Control Equipment. Hence, the proponent is requested to submit details of the above. |
| Date Created: | 2024-07-24 16:50:41.741 |
| File Note: | As per process flow chart submitted, Boiler is proposed to be installed. But, the proponent has not submitted details of capacity of Boiler and its Air Pollution Control Equipment. Hence, the proponent is requested to submit details of the above. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | TSPCB004 |
| Reject: | false |
| Reject Note: | |
| Role: | RO EE |