Show ApplicationProcessingDetails

Id: 5375643
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-08-23 15:39:16.082
File Note: As per the report it is noticed that the industry has obtained EC for expansion activity with a project cost of 4.5 crores. The existing project cost is 19.65 crores which is more than 5.0 crores. Hence, the application is returned to RO with instructions to forward the report to Board office as per delegation of powers.
Inspection: false
Inspection Note:
Officer: TSPCB017
Reject: false
Reject Note:
Role: ZO HYD JCEE