| Id: | 5766429 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The proponent has not submitted site plan, process flow chart and proper land documents. The proponent has paid CFE fee of Rs.2000/-, but the actual CFE fee to be paid is Rs.3200/- under Orange category with the investment of Rs.0.20 Cr. Hence the industry shall pay balance of Rs.1200/-. |
| Date Created: | 2025-02-06 15:03:19.707 |
| File Note: | The proponent has not submitted site plan, process flow chart and proper land documents. The proponent has paid CFE fee of Rs.2000/-, but the actual CFE fee to be paid is Rs.3200/- under Orange category with the investment of Rs.0.20 Cr. Hence the industry shall pay balance of Rs.1200/-. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | TSPCB031 |
| Reject: | false |
| Reject Note: | |
| Role: | RO EE |