Clarification Note: |
The industry shall submit the following details for further processing of application:-
i. Self certification.
ii. Registered lease document.
iii. Air pollution sources and it's control measure details.
iv. Water consumption (for process, dust suppression and domestic), Waste water generation, treatment and disposal details.
v. As per the TOPO plan submitted by the industry the proposed site is adjacent to the Road. As per the siting Guidelines from Transportation / Communication System the industry shall follow the as below:
The following width of buffer zone shall be maintained from the Road Land Boundary*:
1. National Highways – 50 Mts., 2. State Highways – 40 Mts., 3. MDR / Village Road – 20 Mts.
*Road Land Boundary means the boundary of the road upto which land is acquired for road purposes.
Accordingly, the industry shall submit the revised Topo plan showing the Distance from the road to the boundary of proposed site.
vi. Proposed greenbelt details.
|
File Note: |
The industry shall submit the following details for further processing of application:-
i. Self certification.
ii. Registered lease document.
iii. Air pollution sources and it's control measure details.
iv. Water consumption (for process, dust suppression and domestic), Waste water generation, treatment and disposal details.
v. As per the TOPO plan submitted by the industry the proposed site is adjacent to the Road. As per the siting Guidelines from Transportation / Communication System the industry shall follow the as below:
The following width of buffer zone shall be maintained from the Road Land Boundary*:
1. National Highways – 50 Mts., 2. State Highways – 40 Mts., 3. MDR / Village Road – 20 Mts.
*Road Land Boundary means the boundary of the road upto which land is acquired for road purposes.
Accordingly, the industry shall submit the revised Topo plan showing the Distance from the road to the boundary of proposed site.
vi. Proposed greenbelt details.
|