| Id: | 6015848 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The proponent has not submitted capacity of Boiler and its control equipment and not submitted details of ETP, STP proposed in the application & not submitted solid waste generation details and disposal. The industry shall submit the same for further processing of application |
| Date Created: | 2025-06-20 15:31:10.159 |
| File Note: | The proponent has not submitted capacity of Boiler and its control equipment and not submitted details of ETP, STP proposed in the application & not submitted solid waste generation details and disposal. The industry shall submit the same for further processing of application |
| Inspection: | false |
| Inspection Note: | |
| Officer: | TSPCB022 |
| Reject: | false |
| Reject Note: | |
| Role: | ro ee |