Id: | 6030996 |
Approve: | false |
Approve Note: | |
Clarification: | true |
Clarification Note: | After pre-scrutiny of the application, it was observed that you have not mentioned Production capacity in the self certification document and to pay balance CFE fee of Rs.1,66,000/-. Hence you are directed to submit production capacity in self certification document and to pay balance CFE fee for further processing of application which is mandatory |
Date Created: | 2025-06-28 14:50:00.785 |
File Note: | After pre-scrutiny of the application, it was observed that you have not mentioned Production capacity in the self certification document and to pay balance CFE fee of Rs.1,66,000/-. Hence you are directed to submit production capacity in self certification document and to pay balance CFE fee for further processing of application which is mandatory |
Inspection: | false |
Inspection Note: | |
Officer: | TSPCB015 |
Reject: | false |
Reject Note: | |
Role: | RO WGL EE |