| Clarification Note: |
The proponent has not submitted process flow details, self certification, site plan. As per the application, it was observed that the applicant is proposing for manufacture of paints by mxing and blending. However, as per G.O.Ms.No.4, dt:20.01.2018 (amendment of G.O.Ms.No.20), the proposed activity is not excempted to establish within ORR i.e., IDA Bollaram.In view of the above, the application is returned. |
| File Note: |
The proponent has not submitted process flow details, self certification, site plan. As per the application, it was observed that the applicant is proposing for manufacture of paints by mxing and blending. However, as per G.O.Ms.No.4, dt:20.01.2018 (amendment of G.O.Ms.No.20), the proposed activity is not excempted to establish within ORR i.e., IDA Bollaram.In view of the above, the application is returned. |