| Clarification Note: |
After pre-scrutiny, it was observed that the proponent has not submitted the details of the detailed process description, wastewater treatment, boiler & air pollution control equipment & solid waste disposal and has to pay the balance CFE fee of Rs. 10,600/-. Hence, you are hereby directed to submit the above mentioned details and pay the balance CFE fee for further processing of the application. |
| File Note: |
After pre-scrutiny, it was observed that the proponent has not submitted the details of the detailed process description, wastewater treatment, boiler & air pollution control equipment & solid waste disposal and has to pay the balance CFE fee of Rs. 10,600/-. Hence, you are hereby directed to submit the above mentioned details and pay the balance CFE fee for further processing of the application. |