Show ApplicationProcessingDetails

Id: 6437430
Approve: false
Approve Note:
Clarification: true
Clarification Note: After scrutiny of the application, it was observed that, the applicant not submitted Auditors report as per the project cost in CFE order and also not submitted condition wise compliance report if Schedule-B conditions of CFE order is mandatory to process the application. pl submit the same immediately to process the application.
Date Created: 2026-02-21 11:41:31.932
File Note: After scrutiny of the application, it was observed that, the applicant not submitted Auditors report as per the project cost in CFE order and also not submitted condition wise compliance report if Schedule-B conditions of CFE order is mandatory to process the application. pl submit the same immediately to process the application.
Inspection: false
Inspection Note:
Officer: TSPCB015
Reject: false
Reject Note:
Role: RO WGL EE