Show ApplicationProcessingDetails

Id: 6514556
Approve: false
Approve Note:
Clarification: true
Clarification Note: After pre-scrutiny of the application, it was observed that the production capacity mentioned in the self-certification and the application are not same. Hence, you are hereby directed to rectify the above-mentioned shortfall, pay the balance CFE fee of Rs. 10,200/-, and resubmit the application for further processing
Date Created: 2026-04-01 13:01:16.443
File Note: After pre-scrutiny of the application, it was observed that the production capacity mentioned in the self-certification and the application are not same. Hence, you are hereby directed to rectify the above-mentioned shortfall, pay the balance CFE fee of Rs. 10,200/-, and resubmit the application for further processing
Inspection: false
Inspection Note:
Officer: TSPCB015
Reject: false
Reject Note:
Role: RO WGL EE